Which of the following is NOT an output of “Realising the Benefits”?
  1. Achievement of outcomes
  2. Risks and issues managed
  3. Benefit measures
  4. Changes in operations
Explanation
Answer - B - Risks and issues managed is not an output of “Realising the Benefits.”

Key Takeaway: “Realising the Benefits” is concerned with managing the benefits from their initial identification to their successful realisation. Risks and issues managed is an output of “Managing the Tranches.”