Which of the following is NOT a principle of programme risk management?
  1. Understand the programme context Risk change
  2. Capture all project risks centrally
  3. Involve stakeholders
  4. Monitor for early warning indicators
Explanation
Answer - B - “Capture all project risks centrally” is not a principle of programme risk management.

Key Takeaway: Risks and issues in the projects will typically be handled by the projects’ problem/incident reporting mechanisms, only being escalated to the programme level should the project be unable to resolve them.