To which process group does the Acquire Program Team belong?
  1. Human Resource
  2. Planning
  3. Initiating
  4. Executing
Explanation
Answer - D - The Acquire Program Team process belongs to the Executing process group.

Key Takeaway: Remember that the program team consists of the program manager and program team members who are ultimately responsible for the program. To acquire these people means literally to obtain or hire the program team who will be responsible for the work.