Which of the following do progress controls help with?

  1. Quality controls
  2. Authorization of further work
  3. Problem detection and risk identification
  4. Comparing the level of achievement with the plan
  1. 1, 4
  2. 3, 4
  3. 1, 2, 4
  4. 2, 3, 4
Explanation

Answer: D - Quality controls are, of course, part of the Quality theme.

Key takeaway: The Progress theme allows planned objectives to be tracked against those achieved, to keep control of any unacceptable deviations from the plan, and to provide project forecasts. As part of these controls, it is necessary to obtain authorisation for any further work so that it does not impact on the delivery of the original plan.