PgMP Program Management

Category - Domain 4

Which of the following are work results an output of?
  1. Perform Quality Assurance
  2. Develop Program Team
  3. Direct and Manage Program Execution
  4. Monitor and Control Program Work
Explanation
Answer - C - Work results are an output of the Direct and Manage Program Execution process.

Key Takeaway: The Direct and Manage Program Execution process performs-or implements-all of the plans heretofore made in your program management plan. The main purpose of this process is to produce the program deliverables by properly and efficiently executing the program management plan, implementing change requests in a timely and organized fashion, implementing the proper methods and quality standards, delivering status information on the program’s deliverables and processes, and promptly resolving any issues that may arise.