Which is NOT an input to the Acquire Program Team process?
  1. Staffing assignments
  2. Program schedule
  3. Program budget
  4. Staffing management plan
Explanation
Answer - A - Staffing assignments are not an input to the Acquire Program Team process.

Key Takeaway: The Acquire Program Team process is literally the process of obtaining the key players who will participate in a given program. The inputs to the Acquire Program Team process are the staffing management plan (from the Human Resource Planning process), the program budget (from the Cost Estimating and Budgeting process), and the program schedule (from the Schedule Development process).