Lessons learned are which of the following?
  1. Output of the Component Closure process
  2. Output of the Contract Closure process
  3. Output of the Final Performance Review process
  4. Input to and output of the Close Program process
Explanation
Answer - D - Lessons learned are an input to and an output of the Close Program process.

Key Takeaway: A list of lessons learned is compiled during the program review and is also a possible output from several program management processes. These lessons are reviewed, analyzed, and then hopefully integrated into future program management scenarios. Any truly significant lessons learned are discussed at length in the program’s closure report.