PgMP Program Management

Category - Domain 5

Which is NOT an input to the Resource Control process?
  1. Cross-charges
  2. Lease agreements
  3. Performance reports
  4. Program management plan
Explanation
Answer - A - Cross-charges are not an input to the Resource Control process.

Key Takeaway: The Resource Control process manages all the program resources and the associated cost as prescribed by the program management plan. The input to the Resource Control process includes: lease agreements, requirements for equipment facilities, material, and personnel, program management plan, resource management plan, staffing management plan, program budget, ad performance reports. Cross-charges are an output of the Resource Control process.
Was this helpful? Upvote!
Login to contribute your own answer or details