PgMP Program Management

Category - Domain 5

Which is NOT an input to the Perform Quality Control process?
  1. Quality checklists
  2. Inspection reports
  3. Work results
  4. Performance reports
Explanation
Answer - B - Inspection reports are not an input to the Perform Quality Control process.

Key Takeaway: The Perform Quality Control process is used to monitor certain program deliverables (results, services, products, and benefits) to see if they meet the quality requirements. The input to the Perform Quality Control process includes: quality checklists, quality management plan, performance reports, and work results. Inspection reports are included in the output of the process.