When a design firm has a project that their company has designed, who is responsible for the scheduling of the construction?
  1. The owner of the project as there many subs on the job.
  2. The design firm is in charge of all the schedules.
  3. The contractor, however with the design firm able to estimate the time for the entire project.
  4. The contractor is in complete control with no interference.
Explanation
Answer: C - The Contractor, however with the design firm able to estimate the time for the entire project so the client has an idea of how long it should take.