PgMP Program Management

Category - Domain 3

Raymond Beetlebush is a program manager discussing the topic of risk with his colleagues. Which is NOT a true statement about risk?
  1. Risks stem from uncertainty
  2. All risks pose threats to a program
  3. Risks must be managed both at the program level and at the projects level
  4. Risks have impact on accomplishing the program objectives
Explanation
Answer - B - The statement, “All risks pose threats to a program,” is not a true statement about risk.

Key Takeaway: Risks are uncertain event that will either have a positive or negative effect upon the completion of a program or its subsidiary projects-if the event occurs. Risks come from uncertainty, they are managed at both the program and project level, and risks always impact whether or not a team can accomplish program objectives. Although some risks pose a threat to the program, some risks also have positive ramifications on a given program.