36. True or false: Progressive Elaboration is the process of taking a project from an abstract idea or concept to a detailed work package.
  1. True
  2. False
37. For which of the following can you have a baseline?
  1. Scope
  2. Schedule
  3. Cost
  4. Quality
  5. Technical
38.

A diagram featuring a hirerarchical model in which major aspects of a task branch off into their smaller components, with each level labelled by number, could be graphical representation of what key project management document?

  1. Project charter
  2. Work Breakdown Structure
  3. WBS Dictionary
  4. Hierarchical project matrix
39. John is heading up a project on Separately Mangled Accounts, a web platform that allows users to choose their own investments. His project requirements were laid out weeks ago, but he’s just found out from the Product Manager that they want to add two more options before his project is completed. Which has been impacted the most by this sudden news?
  1. Project scope
  2. Product scope
  3. Scope baseline
  4. Periscope
  5. Project charter
40. Sherri Bobbins is formulating her scope management plan for his project. To develop a well-rounded plan she’ll use all of the following, except:
  1. Product analysis
  2. Stakeholder analysis
  3. Scope definition
  4. Benchmarks