201.

What is not true for change requests?

  1. Change requests are always a sign of bad planning and should be avoided.
  2. Change requests can be initiated by external factors, such as regulatory changes.
  3. Change requests are a formal process used to document and manage changes to a project.
  4. Change requests may be necessary to address unforeseen issues or to improve project outcomes.