191. Which is not considered in effective means to monitor and control projects?
  1. Maintaining issue logs
  2. Creating forecasts
  3. Holding regular inspections
  4. Getting status updates from project participants at weekly meetings
  5. These are all effective.
192. Which best signals the completion of a project from the client’s point of view?
  1. When project documents are indexed and archived
  2. When resources are released
  3. When the project receives formal sign-off
  4. When lessons learned are documented
  5. When project funds are completely expended
193. What is the primary objective of the Closing Process?
  1. Ensure that all of the project’s requirements have been satisfied
  2. Manage stakeholders
  3. Do performance appraisals
  4. Take another look at existing risks
194. Which of the following are part of the perform quality control process? Select all that apply:
  1. Assessing the effectiveness of project control systems
  2. Performing re-work to meet quality standards
  3. Authorize work
  4. Make payments to a vendor
  5. Monitor the effectiveness of risk response plans
195. Which of the following processes are part of the Scope Verification process? Select all that apply:
  1. Update the project management plan
  2. Analyze schedule variances
  3. Verifying the quality of a deliverable
  4. Track and report performance of individual resources
  5. Corrective action