156. Another company makes 1,000,000 parts. They’re a low cost provider, and thus they’re shooting for 2 sigma quality. Fewer than ___ out of a million defective parts would be the threshold they are trying to beat.
  1. 47,000
  2. 45,400
  3. 4,540
  4. 45
  5. 2
157. True or false: A good project manager emphasizes inspection over prevention.
  1. True
  2. False
158. Boris wants to figure out how much more his company should invest into the quality of a certain product. What tool would be most effective for this exercise?
  1. Fishbone diagram
  2. Control chart
  3. Run chart
  4. Pareto chart
  5. Marginal analysis
159. What is mutual exclusivity?
  1. If one event occurs, the other cannot
  2. A rule of dating
  3. A measure of variation
  4. A conclusion from a control chart
  5. A conclusion from a scatter diagram
160. What type of organization would project manager have the least power in which form of organization?
  1. Weak matrix
  2. Balanced matrix
  3. Projectized
  4. Functional