166. Project team members are integral to a project’s success. Which of the following should project team members NOT do?
  1. Close out stages of a project
  2. Attend project meetings
  3. Help define requirements
  4. Define the scope of a project
167. Which of the following is NOT a task that Project Managers would be responsible for with respect to their staff?
  1. Commending/rewarding staff for good performance
  2. Writing job descriptions for project-related positions
  3. Ensuring staff members get appropriate training
  4. Pulling a team member off of a project to be re-allocated elsewhere
  5. All of the above
168. John the Project Manager has been dealing with a lot of opposition with respect to getting the resources he needs because the company is typically stingy with spending money. This type of problem can be categorized as a(n):
  1. Dysfunctional management
  2. Human resource irresponsibility
  3. Enterprise environmental factor
  4. Organizational breakdown
169.

A responsibility assignment chart is used to clarify team members’ responsibilities. What does this chart NOT show?

  1. Team member names
  2. Tasks
  3. Primary and secondary responsibilities
  4. Time frames to complete task
  5. All of the above
170. A Staffing Management Plan is comprised of all the following EXCEPT:
  1. Addresses safety hazards and how staff members are to deal with them
  2. Outlines training needs of team members
  3. Indicates how resources will be obtained
  4. Addresses how to deal with belligerent sponsors
  5. All of the above