Mr. Newbie has recently been asked to join the Business Continuity Planning team. As his first assignment, he is tasked with creating a list of potential threats for the company and ranking them. What phase of the project is he working on?
  1. Business Impact Analysis
  2. Risk Assessment
  3. Strategic Planning
  4. Critical Process Planning
Explanation
Answer: B - Mr. Newbie is working on a Risk Assessment. The Risk Assessment identifies key threats to the business, such as floods or terrorist attacks, and then ranks them based on factors such as likelihood of occurrence and severity should the event actually occur.

The Risk Assessment evaluates potential threats and ranks them while the Business Impact Analysis focuses on the different processes within the business and how they will recover should a crisis occur. While they are both key foundations for creating a successful Business Continuity Plan, they are two distinct and separate analyses.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz