PMI PMP Project Management

Category - Scope Management

True or false: Using PERT analysis, the way to calculated estimated duration or cost is by averaging estimates of the optimistic, medium, and pessimistic projections?

  1. True
  2. False
Explanation

Answer: False. PERT is calculated by using the following formula:

Opt + 4 x Med + Pess
--------------------------------------
6

Key Takeaways: This places emphasis on most realistic emphasis, but allows for major variation. For instance, if you know there is one thing that might go wrong and set the project way back, you can have a high pessimistic estimate. If your project is like a portfolio of estimates, then you should a distribution of tasks being on time, early and late. If they’re all coming in late, there are either major systemic issues with the project or with your estimating.

Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz