Which role(s) has/have ultimate authority on the Project Board?
  1. Senior Supplier
  2. Senior User
  3. Executive
  4. Joint authority
Explanation
Answer: C - Executive. The project is ultimately controlled and paid for by the business, which is represented by the Executive.

Key takeaway: Although the Project Board generally makes decisions together, it is not a democracy. The Senior Supplier and Senior User can be overruled by the Executive, even if they are both united against him.