For which of the following is the Business Change Manager responsible?
  1. Managing communications with the Programme Board
  2. Advising and supporting the SRO
  3. Managing the programme’s budget
  4. Ensuring business ownership of Benefit Profiles
Explanation
Answer - D - The Business Change Manager is responsible for ensuring business ownership of Benefit Profiles.

Key Takeaway: The Business Change Manager’s responsibilities are primarily focused on benefits. The benefits need to be defined and realised in terms of measured improvements in business performance.