Which of the following products is NOT created during the Initiating a Project process?
  1. Quality Management Strategy
  2. Lessons Log
  3. Project Product Description
  4. Exception Plan
Explanation
Answer: D - Exception Plan. At this early point in the project, is no detailed plan to have an exception to.

Key takeaway: Almost all of the key documents are created during the Initiating a Project process, although most of them will be updated at various points throughout the life of the project.