Which process provides information to the Project Board to allow them to assess the continuing viability of the project?
  1. Controlling a Stage.
  2. Directing a Project.
  3. Managing a Stage Boundary.
  4. Managing Product Delivery.
Explanation
Answer: C - Managing a Stage Boundary. This is the point at which the Business Case is reviewed.

Key takeaway: In line with the PRINCE2 principle of Continued Business Justification, the Business Case is updated during the Managing a Stage Boundary process. This is then reviewed by the Project Board-if the justification is no longer valid, then the project should be closed.