Project scope can be limited by the following factors EXCEPT:
  1. geography
  2. demographics
  3. organizational structures
  4. ten year financial projects
Explanation
Answer: D - Project scope can be limited by a number of factors including geography, demographics and organizational structures.

Key Takeaway: A project scope details the time and resources that are necessary to turn inputs into a product or a service. Project scope can be limited by a number of factors that include geography, demographics and organizational structures. Other sources of limitation include process boundaries, relationships with stakeholders such as customers, vendors, and contractors.