A risk response plan for a program is an output of which of the following?
  1. Risk Management Identification
  2. Risk Management Response Planning
  3. Risk Management Analysis
  4. Risk Management Monitoring and Controlling
Explanation
Answer: B - A risk response plan is an output of Risk Management Response Planning.

Key Takeaway: The Risk Management Response Planning process includes effective risk-response planning. The most common risks arise from the program schedule and program cost. Because of this, the key input items for the Risk Management Response Planning process are the program schedule, the PWBS, and the program budget.