Which is NOT an output item of the Initiate Program process?
  1. Project Selection criteria
  2. Program charter
  3. Benefits realization plan
  4. Detailed program scope statement
Explanation
Answer - D - A detailed program scope statement is not an output item of the Initiate Program process. It is prepared during the Scope Definition process.

Key Takeaway: The detailed program scope statement is not an output item of the Initiate Program process. The true output items of the Initiate Program process includes: a communication plan for managing benefits, a definition for each benefit, mapping between program outcomes and benefits, procedures to measure benefits, the roles and responsibilities for managing the benefits, and how to transition the responsibilities to the organization’s ongoing operations after the program is terminated.