You have tested an upgrade plan in a controlled environment and are ready to do the upgrade in the production environment. Which of the following should you do before you take a server and its resources offline?
  1. Disconnect users from the server.
  2. Notify users of the server downtime.
  3. Disconnect the server.
  4. Directly implement the upgrade plan.
Explanation
Answer - B - Before you take a server and its resources offline, you should notify users of the server downtime.

Key Takeaway: To enable smooth functioning of the upgrade plan and ensure that users are not severely affected, you should notify the users about the timing and duration of the upgrade process. Since they will not be able to access the server during the upgrade, you need to give them enough time to make all backup arrangements and disconnect from any server resources.