Which role confirms stage and project progress against agreed tolerances?
  1. Project Board
  2. Project Assurance
  3. Project Support
  4. Project Manager
Explanation
Answer: B - Project Assurance.

Key takeaway: It is the role of Project Assurance to provide independent assurance to the Project Board as to the status of the project. It is for this reason that the Project Assurance and Project Manager roles must not be held by the same person (or people).