Which of these is NOT one of the four primary risk management processes?
  1. Implement
  2. Identify
  3. Plan
  4. Estimate
Explanation
Answer - D - “Estimate” is not one of the four primary risk management processes.

Key Takeaway: The fourth primary risk management process is “Assess,” which comprises the steps “Estimate” and “Evaluate.”