Which of the following would you find in a Programme Plan?
  1. Criteria to assess programme success
  2. Guidelines to ensure the appropriate use of audits and health checks
  3. Cross-reference to the Risk Register to explain any planning contingencies that have been made to mitigate risk
  4. Budgeting requirements for quality
Explanation
Answer - B - You would find guidelines to ensure the appropriate use of audits and health checks in a Programme Plan.

Key Takeaway: The other items would all appear in a Quality Management Strategy.