Which is NOT included in the input to the Close Program process?
  1. Certificate of program completion
  2. Product description
  3. Program management plan
  4. Approved deliverables
Explanation
Answer - C - Program management plan is not an input to the Close Program process.

Key Takeaway: The Close Program process involves putting together the closure documents and reviewing them with the customer, the program sponsor or both to obtain acceptance of the outcome of the program. The input to the Close Program process include: approved deliverables, program management plan, program scope statement, product description, status reports, and lessons learned. The certificate of program completion is an output of the Close Program process.