Which of the following is NOT a responsibility of the Programme Office?
  1. Risk and issue tracking
  2. Holding master copies of all programme information
  3. Maintaining the list of stakeholders and their interests
  4. Reporting progress of the programme at regular intervals to the SRO
Explanation
Answer - D - Reporting progress of the programme at regular intervals to the SRO is not a responsibility of the Programme Office.

Key Takeaway: Reporting progress of the programme at regular intervals to the SRO is the responsibility of the Programme Manager.
Was this helpful? Upvote!