PgMP Program Management

Category - Domain 6

Which is NOT included in the input to the Contract Closure process?
  1. Delivery notices
  2. Termination notice
  3. Certificate of contract completion
  4. Acceptance reports
Explanation
Answer - C - Certificate of contract completion is not included in the input to the Contract Closure process.

Key Takeaway: The Contract Closure process is used to close the contracts executed during a program according to the contract terms and conditions. In order to perform the Contract Closure process the following inputs are necessary: termination notice, delivery notices, contract performance records, and acceptance records. The certification of contract completion and the contract termination documentation are outputs of this process.
Was this helpful? Upvote!
Login to contribute your own answer or details