What is phase three of the program life cycle called?
  1. Pre-program setup
  2. Program setup
  3. Initiating
  4. Establish program infrastructure
Explanation
Answer - D - Phase three of the program life cycle is called establish program infrastructure.

Key Takeaway: Five phases make up a program life cycle: pre-program setup, program setup, establishing program infrastructure, delivering incremental benefits, and closing the program. A program may uses processes from the nine knowledge areas, and process groups are closely related to the program phases, but only these five phases make up a program life cycle.