What is a standard range for a Rough Order of Magnitude estimate?
Answer: B - The standard range for a Rough Order of Magnitude Estimate is from -25% to +75%. Key Takeaway: While that range sounds wide, it is actually very easy to miss in the early stage. A good project manager does in-depth analysis before issuing Rough Order of Magnitude estimates. Note that this guideline suggests that you’re better off missing on the high side than the low side.