In which phase is the infrastructure for monitoring and controlling the constituent projects in a program established?
  1. One
  2. Two
  3. Three
  4. Four
Explanation
Answer -D - the infrastructure for monitoring and controlling the constituent project in a program is established in phase four.

Key Takeaway: Five phases make up a program life cycle: pre-program setup, program setup, establishing program infrastructure, delivering incremental benefits, and closing the program. Establishing the infrastructure for monitoring and controlling constituent projects in a program is handled in phase four: Delivering incremental benefits. Although it sounds like this should be handled in Phase Three: Establishing Program Infrastructure, that only refers to the program’s infrastructure-not that of the individual projects. Establishing the infrastructure for monitoring and controlling individual projects happens in the Delivering Benefits phase-phase four.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz