Consider the differences between portfolios, projects, and programmes. Which of these characteristics is least applicable to a programme?
  1. Benefit delivery will dominate, with significant focus on the rigour of benefit profiling and realisation
  2. Planning will be viewed from outcome dependency and resolving conflicts
  3. Quality focus will be on control and improvement
  4. Stakeholder engagement will be focused at all levels in the organisation and key external influencers
Explanation
Answer - B - “Planning will be viewed from outcome dependency and resolving conflicts” is least applicable to a programme.

Key Takeaway: Viewing planning from outcome dependency and resolving conflicts is more applicable to a portfolio.