At what point is a Stage Plan updated with actuals?
  1. During the Managing a Stage Boundary process.
  2. As soon as actuals are received from a Work Package.
  3. Once a Work Package has been delivered.
  4. Once a Work Package has been approved.
Explanation
Answer: B - As soon as actuals are received from a Work Package.

Key takeaway: Updated information can be received by a Project Manager throughout the life of a Work Package: from the approval of the Work Package itself, through reviews of the status, and Checkpoint Reports. Remember that several Work Packages may be running concurrently in a single stage, and the Project Manager needs to keep updated on the progress of all of them.