A resource histogram is used in which process?
  1. Resource Optimization
  2. Develop Program Management Plan
  3. Resource Planning
  4. Interface Planning
Explanation
Answer - C - A resource histogram is used in the Resource Planning process

Key Takeaway: A resource histogram is a graph displaying resource requirements. A resource histogram can include the number of hours that an employee or team will need to work on a given program or project, levels of various resources needed for the project, and/or a summary of resource requirements for the program. A resource histogram is very useful in the Resource Planning process.