Project team members are integral to a project’s success. Which of the following should project team members NOT do?
  1. Close out stages of a project
  2. Attend project meetings
  3. Help define requirements
  4. Define the scope of a project
Explanation
Answer: d - Project team members contribute to many stages of a project, including: aiding to define requirements, attending relevant meetings and helping to close out phases of the project, but they do not define the scope of the project. This is done by the project’s Sponsor.

Key Take Away: Allowing your scope to be amended easily, will inevitably result in several issues - the largest and most costly being Scope Creep.