16. Which role is responsible for realising the benefits?
  1. Programme Manager
  2. Senior Responsible Owner
  3. Sponsoring Group
  4. Business Change Manager
17. Which of the following is NOT an output of “Realising the Benefits”?
  1. Achievement of outcomes
  2. Risks and issues managed
  3. Benefit measures
  4. Changes in operations
18. Which of these is NOT an output of “Closing a Programme”?
  1. Final tranche prepared
  2. Programme team disbanded
  3. Lessons learned
  4. Plan for post-programme benefits review
19. Who is responsible for confirming programme closure?
  1. Senior Responsible Owner
  2. Programme Manager
  3. Business Change Manager
  4. Programme Office
20. Which of the following is NOT one of MSP’s four suggested levels of stakeholder engagement?
  1. Maintain interest
  2. Active consultation
  3. Formally approve
  4. Keep informed