Who is responsible for confirming programme closure?
  1. Senior Responsible Owner
  2. Programme Manager
  3. Business Change Manager
  4. Programme Office
Explanation
Answer - A - The Senior Responsible Owner is responsible for confirming programme closure.

Key Takeaway: The SRO will confirm programme closure when the Business Case has been satisfied, all projects have completed satisfactorily, and any remaining handover or transition activities have been defined and assigned.