101. Which of the following should NOT be included in a Business Case?
  1. Value of the benefits
  2. Risks to achieving them
  3. Stakeholders
  4. Costs of delivering the Blueprint
102. Which of the following should not be part of the Programme Plan?
  1. Project timescales, costs, outputs, and deliverables
  2. Transition plans
  3. Monitoring and control activities and performance targets
  4. The detailed schedules for every project in the dossier
103. Which of the following is true of a Programme Plan?
  1. It is a master project plan.
  2. It is a Gantt chart.
  3. It helps with the detailed management of each project in the programme.
  4. It is a key control document that covers projects and activities.
104. Which of these would you NOT find in a Risk Management Strategy?
  1. Scales for estimating probability
  2. The identification of risk actionees
  3. Relevant early-warning indicators
  4. Guidance on how proximity for risks is to be assessed
105. Which of the following would you find in a Programme Plan?
  1. Criteria to assess programme success
  2. Guidelines to ensure the appropriate use of audits and health checks
  3. Cross-reference to the Risk Register to explain any planning contingencies that have been made to mitigate risk
  4. Budgeting requirements for quality