Carrie’s friend was just in an earthquake while at work. This got Carrie thinking that her company needed a business continuity plan. She decided to put someone in charge of developing, implementing, and testing the new plan. What is the proper name for the person put in charge?
Explanation
Answer: C - The business continuity coordinator develops, implements, and tests the continuity and disaster recovery plans. This individual also puts together a team or committee. The team must be comprised of people who are familiar with the different departments within the company because each department is unique in its functionality and has distinctive risks and threats. The committee should be made up of representatives from at least the following departs: business units, senior management, IT department, communications department, and legal department.