PMI PMP Project Management

Category - Project Processes

Which of the following tasks could be part of the process of managing stakeholders? Select all that apply:
  1. Update the project management plan
  2. Communicate with stakeholders
  3. Analyze schedule variances
  4. Maintain issue log
  5. Maintain communications management plan
Explanation
Answer: B, D, E - Communicate with stakeholders, maintain issue log and maintain communications management plan are all processes under Manage Stakeholders.

Update the project management plan and analyze schedule variances are part of the schedule control process.

Key takeaway: We figured you got “communicate with stakeholders”. Remember that maintaining an issue log and a communications plan fall into the Manage Stakeholders process.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz