Which of the following are examples of scope verification activities?
  1. Quality audit
  2. Formal deliverable acceptance
  3. Statement of Work
  4. Scope management plan
  5. All of the above
Explanation
Answer: A, B - Quality audits and formal deliverable acceptance are both examples of scope verification.

Key Takeaway: Scope verification generally requires customer acceptance of a project deliverable. Checking for quality, completeness and accuracy of the completed work as it relates to the original scope is what scope verification is all about.