Which of the following tasks could be part of the Scope Control process? Select all that apply:
  1. Adjust the scope baseline
  2. Re-planning
  3. Analyze variances
  4. Maintain issue log
  5. Maintain communications management plan
Explanation
Answer: A, B, C - Updating the scope baseline, re-planning and analyze variances fall under the Scope Control processes.

Maintain issue log and maintain communications management plan are all processes under Manage Stakeholders. These are hard ones, so we’re including them multiple times in the answers.

Key takeaway: We figured you got “communicate with stakeholders”. Remember that maintaining and issue log and a communications plan fall into the Manage Stakeholders process.