Which of the following is NOT an input to “Defining a Programme”?
  1. Programme Preparation Plan
  2. Programme Brief
  3. Confirmed Business Case
  4. Emerging programme current status and plans
Explanation
Answer - C - Confirmed Business Case is not an input to “Defining a Programme.”

Key Takeaway: Approved Business Case is one of the outputs of “Defining a Programme.”