What is the full name of the P3M3 maturity model?

  1. The Procedural, Programme, and Project Management Maturity model
  2. The Portfolio, Process, and Project Management Maturity model
  3. The Process, Procedure, and Programme Management Maturity model
  4. The Portfolio, Programme, and Project Management Maturity model
Explanation

Answer: D - “The Portfolio, Programme, and Project Management Maturity model” is the full name of the P3M3 maturity model.

Key Takeaway: This model identifies five levels of maturity that an organisation passes through as it seeks to achieve and improve on best practice.