Part of the project output to the strategic objective chain is in which order?
  1. End Benefit -> Outcome -> Business Change
  2. Business Change -> End Benefit -> Outcome
  3. Business Change -> Outcome -> Intermediate Benefit
  4. Outcome -> Business Change -> Intermediate Benefit
Explanation
Answer - C - Part of the project output to strategic objective chain is in the order “Business Change -> Outcome -> Intermediate Benefit.”

Key Takeaway: The full sequence is “Project Output -> Business Change -> Outcome -> Intermediate Benefit -> End Benefit -> Strategic Objective.”