When are programmes normally closed?
  1. When all projects are finished
  2. When all products are delivered
  3. When the end goal has been achieved, new capabilities have been delivered and some benefits have been realised
  4. Never
Explanation
Answer - C - Programmes are normally closed when the end goal has been achieved, new capabilities have been delivered, and some benefits have been realised.

Key Takeaway: Some benefits will have been realised during the running of the programme. However, the majority of the benefits may not be fully realised until some time after the last project has been delivered.